Monthly News - Nef Sapanca

Our valued customer,

We wanted to share the latest news about Nef Sapanca with you.

Reinforced concrete works have been completed in all villas and residences.

Aerated concrete wall manufacturing has been completed in all villas. It is 35% in A1 Block, 65% in A2 Block, and 65% in A3 Block.

Steel roof construction manufacturing has been completed in all villas.

Concrete tile roof cover manufacturing has been completed in all villas.

Facade EPS cladding and painting works have been completed in all villas.

All manufacturing within the scope of villa electrical works has been completed.

All manufacturing has been completed within the scope of villa mechanical works.

Within the scope of finishing works, black plaster works were completed in all villas.

Within the scope of finishing works, gypsum plaster works have been completed in all blocks.

Within the scope of finishing works, suspended ceiling manufacturing has been completed in all villas except D4.

Joinery work has been completed in all blocks.

Within the scope of finishing works, insulation works have been completed in all blocks.

Within the scope of fine works, ceramic works have been completed in other blocks except blocks B8, D4.

Within the scope of finishing works, screed manufacturing has been completed in all villas except D4 villa.

Steel staircase manufacturing has been completed in all blocks.

Facade Railing manufacturing has been completed in all villas except Block D.

Painting works within the scope of finishing works A1, A2, A3, A4, A5, A6, A7, A8, A9, B1, B2, B3, B4, B5, B6, B7, B9, B10, B11, B12, B13, B14, B15 It was completed in blocks B17, C1, C2, C3, C4, C5, C6, C7, C8, C9, C10, C11, C12, C13, E1, E2, E3, E4, E5, E6, E7.

Facade ceramic manufacturing E1,E2, C4, E3,E4, E5, E6, E7,C4,C5,C6,C7,C8,C9,C10,C11 A1, A2, A3, A4, A5, A6, A7, A8, It has been completed in blocks A9, B1, B6, B7, B8, B9, B10, B11, and continues at the level of 70% in blocks C12, C13, C14.
Parquet manufacturing A1,A2,A3,A4,A5,A6,A7,A8,A9,B1,B2,B3,B4, B5, B6,B7,B9, B10,B11, B12, B13, B14, B15, C1, C3, C4, C5, C6, C7, C8, C9, C10, C11, C12, C13, C14, E1, E2, E3, E4, E5, E6, E7 blocks have been completed and B8 is at 50% level.

Indoor door installation B1,B2,B3,B4,B5, B15, C5,C6,C7,C8,C9, C10,C11,C12,C13,A1,A2,A3,A4,A5, B6,B9,B10, It is at 90% level in B11,E2,E3,E4,E5,E6,E7 Blocks. It is at the level of 75% in A6, A8 blocks.

Flat entrance door installation A1,A2,A3,A4,A5 B1,B2,B3,B4,B5 B6, B7, B9, B10,B11, B12, C1,C2,C3, C4, C5, C6, C7, C8, It was completed in villas C9, C10, C11, C12, C14, E1, E2, E3, E4, E5, E6, and E7.

Kitchen cabinet assembly A1,A2,A3,A4,A5,B1,B2, B3, B4, B5, B6,B7, B9, B10,B11, C1, C2,C3 ,C4,C5,C6,C7,C8,C9 Blocks C10, C11, C12, C13, C14, C15, C16, C17, C18, C19, C20, C21, C22, C23, E1, E2, E3, E4, E5, E6, E7 have been completed at 80% level.


Within the scope of landscaping and infrastructure works, environmental drainage in villas and residences has been completed and field filling and leveling works have been completed. Rainwater and sewage
The excavation of the lines and the installation of pipes have been completed. Natural gas infrastructure construction has been completed. Fire Hydrant infrastructure manufacturing has been completed. Electrical infrastructure manufacturing and garden irrigation infrastructure manufacturing continues.

The manufacturing of the sample villas has been completed.

Within the scope of landscape works, vehicle, walking path and parking area manufacturing is at the level of 70% and continues.

Fire pit reinforced concrete manufacturing has been completed in all blocks.

Veranda manufacturing has been completed in E1 and C4 Blocks and is at the level of 90% in C1, C5, C6, C7, C8, C9, C10, C11, C12, B12 villas.

Pergola assembly was completed in A3, B7, B8, B10, C4, C5, C6, C7, C8, C9, C10, C11, C12 blocks.

Pool manufacturing is at the level of 50% in A4, A7, A8, E3, C3, B6, B9, D9, B16, B13, B14 blocks. It is at the level of 20% in A2, C5, C6, C9, C1, C23, D2 blocks.

Dividing wall (enclosure) manufacturing is at the level of 85% throughout the construction site.

Mechanical and Electrical armature, battery and sanitary ware installation has been completed by 45%.

Vegetable Landscape works have been completed in E1 and C4 Blocks.

We will continue to share with you the updated drone images of the project as long as the weather conditions are suitable.

Hope to see you again with new news.