Monthly News - Nef Reserve Gölköy

Greetings, 

We have good news regarding Nef Reserve Gölköy. 

Allow us to begin by informing you that in response to the global COVID-19 (Coronavirus) pandemic, rigorous occupational health measures have been implemented at our construction sites as guided by risk analyses, and all works are being carried out in a safe and healthy manner.

Across the project, 95% of the basic construction is finalized, and fine construction continues. Here are the latest details of the construction at each block:

In Blocks 37 and 38, fine construction, electrical and mechanical works, mechanical facade anchoring, construction of the swimming pool, installation of railings, tile installation on the terrace, window framing and installations, and wood flooring are complete. Woodwork installations of kitchen and bathrooms, landscaping works and glass installations on the terrace railings are at 98% completion. 

In Block 36, wall construction and gypsum plastering, mechanical facade anchoring, window framing, plasterboard walls, installation of natural stone inside the units and in wet areas, suspended ceilings and window installations are complete. The construction of the swimming pool, installation of railings and stone facade sealing are 90% complete. 


In Blocks 34 and 35, aerated concrete walls, gypsum plastering, plasterboard walls, window framing and installations, suspended ceilings, floor heating, electrical and mechanical works, mechanical facade anchoring and the installation of natural stone inside the units and in wet areas are complete. Stone facade sealing, installation of railings and construction of the swimming pool are 95% complete. 

In Blocks 32 and 33, aerated concrete walls, plasterboard walls, gypsum plastering, floor heating installations, window framing and installations, mechanical and electrical works, floor marble installations, mechanical facade anchoring, and tile installation on the terrace are complete. Stone facade sealing is at 95% completion, and construction of the swimming pool, the installation of railings and of natural stones inside the units and wet areas continue.

In Blocks 30 and 31, aerated concrete walls, plasterboard walls, gypsum plastering, floor heating installations, window framing, mechanical facade anchoring, and mechanical and electrical works are complete. Window installations and facade sealing are at 95% completion, and the construction of the swimming pool, installation of railings and flooring, and marble installation in wet areas continue. 

In blocks 27, 28 and 29, aerated concrete walls, gypsum plastering, plasterboard wall and floor heating installation, window framing and installation, and marble installation inside the units and in wet areas are complete. Mechanical facade anchoring and stone facade sealing are at 95% completion, whereas railing installation and pool construction are underway.  

Basic construction for Block 26 is complete. 

In blocks 25, 24, 23 and 22, aerated concrete walls, plasterboard wall, suspended ceiling, marble works for the floors, and window framing are complete. Mechanical and electrical works, mechanical facade anchoring, window framing and installations, pool construction and installation of railings are at 90% completion. 

Basic construction, aerated concrete wall construction and blind casing installation are finalized for Block 21. Mechanical facade anchoring is 76% complete. 

Blocks 19 and 20 serve as our model villas. 

In Blocks 17 and 18, basic construction, aerated concrete walls, blind casing 
installation and plasterboard walls are complete. Reinforced concrete terraces are at 95% completion. Suspended ceilings, electrical and mechanical works, mechanical facade anchoring, railing installation, swimming pool construction and window framing are underway.

In Blocks 15 and 16, basic construction and aerated concrete walls are complete. Mechanical facade anchoring is at 90%. Construction of plasterboard walls and suspended ceilings, pool construction and railing installation, electrical and mechanical works, and window framing are underway. 

In Blocks 13 and 14, basic construction, aerated concrete walls, plasterboard walls and window framing are complete. Mechanical facade anchoring is at 90% and suspended ceilings, electrical and mechanical works, pool construction, and railing installation are underway. 

In Blocks 11 and 12, basic construction, aerated concrete walls and window framing are complete. Plasterboard wall installation, gypsum plastering, mechanical facade anchoring, pool construction, railing installation, electrical and mechanical works, and floor heating installations continue.

In Block 10, aerated concrete walls and window framing are complete. Installation of plasterboard walls, gypsum plastering, mechanical facade anchoring, construction of the pool, and installation of railings and suspended ceilings are underway.

In Block 9, aerated concrete walls, plasterboard walls, mechanical and electrical works, suspended ceilings, gypsum plastering, and window framing are complete. Mechanical facade anchoring, pool construction, and window and railing installations continue. 

In Blocks 7 and 8, aerated concrete walls and blind casing installations are complete. Plasterboard wall construction, mechanical facade anchoring, railing anchoring and pool construction are underway. 

In Block 6, aerated concrete walls are complete. Construction of plasterboard walls, mechanical facade anchoring, electrical and mechanical works, railing anchoring and pool construction continue. 


Basic construction is finalized in Block 5. Construction of aerated concrete walls continues. 

In Blocks 3 and 4, aerated concrete walls, plasterboard walls, gypsum plastering, and window framing are complete. Mechanical facade anchoring, installation of railings, window framing, mechanical and electrical works, and suspended ceilings are underway. 

In Block 2, aerated concrete walls are complete. Plasterboard wall construction, blind casing installation, and electrical and mechanical works continue. 

In Block 1, basic construction and aerated concrete walls are complete. Construction of plasterboard walls, blind casing installations, electrical and mechanical works, and mechanical facade anchoring are underway.


You can view the aerial photographs of the project site by watching the video below.


Stay tuned for more updates.