Monthly News - Nef Reserve Gölköy

Greetings,

We have good news regarding Nef Reserve Gölköy.

Allow us to begin by informing you that in response to the global COVID-19 (Coronavirus) pandemic, rigorous occupational health measures have been implemented at our construction sites as guided by risk analyses, and all works are being carried out in a safe and healthy manner.

Across the project, 90% of the basic construction is finalized, and fine construction continues. Deliveries are planned to begin by December 2021, and the projected date for residential life is May 2022. Here are the latest details of the construction at each block:

In Blocks 37 and 38, aerated concrete walls, gypsum plastering, plasterboard walls, suspended ceilings, window framing and installations, floor heating, electrical and mechanical works, mechanical facade anchoring and natural stone installations inside the units and in wet areas are complete. Stone facade sealing, installation of railings and the construction of the swimming pool are 95% complete.

In Block 36, aerated concrete walls, gypsum plastering, mechanical facade anchoring, window framing, plasterboard walls and the installation of natural stone installations inside the units and in wet areas are complete. Window installations, construction of the swimming pool, installation of railings, and stone facade sealing are 90% complete.

In Blocks 34 and 35, aerated concrete walls, gypsum plastering, plasterboard walls, window framing and installations, suspended ceilings, floor heating, electrical and mechanical works and mechanical facade anchoring are complete. Stone facade sealing, installation of railings and construction of the swimming pool are 90% complete. Indoor natural stone installations have begun. Natural stone installations are at 75% completion and continue inside the units and in wet areas.  

In Blocks 31, 32 and 33, basic construction, aerated concrete walls, plasterboard walls, gypsum plastering, and floor heating installations, window framing and floor marble installations are complete. Window installations and mechanical facade anchoring is at 90% completion, whereas mechanical and electrical works, construction of the swimming pool, the installation of railings and of natural stones inside the units and wet areas continue.

In blocks 27, 28, 29 and 30, aerated concrete walls, gypsum plastering, plasterboard wall and floor heating installations, window framing and marble installations in wet areas are complete. Mechanical facade anchoring and stone facade sealing is at 95% completion, whereas window and railing installations are underway. Natural stone installations continue inside the units and in wet areas. 

Basic construction for Block 26 continues.

In blocks 25, 24, 23 and 22 basic construction, aerated concrete walls, plasterboard wall and framing for the suspended ceiling are complete. Mechanical electrical works, mechanical facade anchoring, window framing and installations, marble works and installation of railings are at 85% completion. Natural stone installations have begun for indoor floors and in wet areas.

Basic construction and aerated concrete wall construction are finalized for Block 21. Facade natural stone works are 70% complete.

Blocks 19 and 20 are finalized and serve as our model villas.

In Blocks 17 and 18, basic construction, aerated concrete walls, blind casing

installation and plasterboard walls are complete. Reinforced concrete terraces are at 95% completion. Suspended ceilings, electrical and mechanical works, mechanical facade anchoring, installation of railings and window framing are underway.

In Blocks 15 and 16, basic construction and aerated concrete walls are complete. Mechanical facade anchoring is at 85%. Construction of plasterboard walls and suspended ceilings, pool construction and railing installation, electrical and mechanical works and window framing are underway.

In Blocks 13 and 14, basic construction, aerated concrete walls and plasterboard walls are complete. Mechanical facade anchoring is at 90% and suspended ceilings, electrical and mechanical works, pool construction, railing installation and window framing are underway.

In Blocks 11 and 12, basic construction and aerated concrete walls, plasterboard walls, gypsum plastering and window framing are finalized. Mechanical facade anchoring is at 80% completion. Pool construction and railing installation continue.

In Blocks 9 and 10, basic construction, aerated concrete walls, plasterboard walls and gypsum plastering are complete. Mechanical facade anchoring, pool construction, railing installation, window framing and suspended ceilings are underway.

In Blocks 6, 7 and 8, basic construction is finalized. Aerated concrete walls are and blind casing installations are complete for Blocks 7 and 8, and continue for Block 6.

Basic construction continues in Block 5.

         

In Blocks 3 and 4, basic construction, aerated concrete walls, plasterboard walls and gypsum plastering are complete. Mechanical facade anchoring, installation of railings, window framing and suspended ceilings are underway.

In Block 2, basic construction and aerated concrete walls are complete.

In Block 1, basic construction and aerated concrete walls are complete. Construction of plasterboard walls, mechanical facade anchoring, thermal sheathing and window framing are underway.

You can view the aerial photographs of the project site by watching the video below

Stay tuned for more updates.