Monthly News - Nef Reserve Gölköy

Greetings,

We have good news regarding Nef Gölköy.

Allow us to begin by informing you that in response to the global COVID-19 (Coronavirus) pandemic, rigorous occupational health measures have been implemented at our construction sites as guided by risk analyses, and all works are being carried out in a safe and healthy manner.

Across the project, 87% of the basic construction is finalized, and fine construction continues. Here are the latest details of the construction at each block:

In Blocks 37 and 38, aerated concrete walls, gypsum plastering, plasterboard walls, suspended ceilings, floor heating, and electrical and mechanical works are complete. Mechanical facade anchoring is at 95%, framing and window installations are at 90%. Stone facade sealing, satin plastering, the installation of railings and the construction of the swimming pool are underway. Marble installations in the bathrooms have begun.

In Block 36, aerated concrete walls, gypsum plastering, plasterboard walls, floor heating, and electrical and mechanical works under the suspended ceiling are complete. Mechanical facade anchoring is at 95% and framing and window installations are at 90% completion. Satin plastering, installation of railings, construction of the swimming pool, and stone facade sealing are underway.

In Blocks 34 and 35, aerated concrete walls, gypsum plastering, plasterboard walls, suspended ceilings, floor heating, and electrical and mechanical works are complete. Mechanical facade anchoring is at 95% and framing and window installations are at 90% completion. Stone facade sealing, installation of railings and construction of the swimming pool are underway. Marble cladding of the bathrooms have begun.

In Blocks 31, 32 and 33, aerated concrete walls, gypsum plastering, plasterboard walls and floor heating installations are complete. Framing and window installations are at 85% and mechanical facade anchoring is at 80% completion. Satin plastering, suspended ceiling and railing installations, mechanical and electrical works, construction of the swimming pool, and stone façade sealing are underway.

In blocks 27, 28, 29 and 30, aerated concrete walls, gypsum plastering, plasterboard walls and floor heating installations are complete. Mechanical facade anchoring and stone facade sealing is at 85% completion, and framing and window installations are at 80% completion. Satin plastering, suspended ceiling and railing installations, mechanical and electrical works, and the construction of the swimming pool are underway.

Excavation works for Block 26 have begun.

For Blocks 22, 23, 24 and 25, aerated concrete walls, gypsum plastering, plasterboard walls and floor heating installations are complete. Mechanical facade anchoring and stone facade sealing is at 70% completion, and framing and window installations are at 65% completion. Satin plastering, suspended ceiling installations, mechanical and electrical works and the construction of the swimming pool are underway.

For Block 21, basic construction and aerated concrete walls are complete.

Blocks 19 and 20 are finalized and serve as our model villas.

In Blocks 17 and 18, basic construction, aerated concrete walls and blind casing framing installations are complete. Reinforced concrete terraces are at 95% completion. Plasterboard walls, and electrical and mechanical works are underway.

In Blocks 15 and 16, basic construction and aerated concrete walls are complete. Plasterboard wall installation will be next and mechanical facade anchoring is underway.

In Blocks 13 and 14, basic construction, aerated concrete walls and blind casing framing installation are complete. Plasterboard wall installation, mechanical facade anchoring, framing and window installations, and electrical and mechanical works are underway.

In Blocks 11 and 12, basic construction and aerated concrete walls are complete. Plasterboard walls are currently being installed.

In Blocks 9 and 10, basic construction, aerated concrete walls and blind casing framing installations are complete. Installation of plasterboard walls and the construction of reinforced concrete terraces are underway. 

In Blocks 7 and 8, basic construction is finished. Aerated concrete walls and blind casing framing installations are underway.

In Blocks 5 and 6, basic construction continues.

In Blocks 3 and 4, basic construction, aerated concrete walls, plasterboard walls and blind casing framing installation are complete. Electrical and mechanical works, mechanical facade anchoring and stone facade sealing, installation of suspended ceilings and gypsum plastering are underway.

In Block 2, basic construction is complete. Construction of aerated concrete walls continue.

In Block 1, basic construction and aerated concrete walls are complete. Mechanical facade anchoring is underway.

You can view the aerial photographs of the project site by clicking the button below.

Project Photos (button)

Stay tuned for more updates.