Greetings, 

We have good news regarding Nef Reserve Gölköy. 

Across the project, 98% of the basic construction is finalized, and fine construction continues. Here are the latest details of the construction at each block:

All the productions in the 38th and 37th blocks have been completed.

In Blocks 37 and 38, fine construction, electrical and mechanical works, mechanical facade anchoring, construction of the swimming pool, railing installation, tile installation on the terrace, window framing and installations, and wood flooring are complete. Woodwork installations of kitchen and bathrooms, landscaping works and glass installations on the terrace railings are at 99% completion. 

In Block 36, wall construction and gypsum plastering, mechanical facade anchoring, window framing and installations, plasterboard walls, installation of natural stone inside the units and in wet areas, suspended ceilings  pool manufacturing, guardrail manufacturing and tile installation on the terrace are complete. The construction of the swimming pool, installation of railings and stone facade sealing are 95% complete. 

In Blocks 34 and 35, aerated concrete walls, gypsum plastering, plasterboard walls, window framing and installations, suspended ceilings, floor heating, electrical and mechanical works, mechanical facade anchoring and the installation of natural stone inside the units railing works, pool manufacturing  and in wet areas are complete. Natural stone facade sealing, installation of railings and construction of the swimming pool are 95% complete. 

In Blocks 32 and 33, aerated concrete walls, plasterboard walls, gypsum plastering, floor heating installations, window framing and installations, mechanical and electrical works, floor marble installations inside the units and wet areas, mechanical facade anchoring, mechanical works, interior and wet area marble cladding works, mechanical facade cladding works, pool manufacturing, railing works and tile installation on the terrace are complete. Stone facade sealing is at 98% completion, and swimming pool construction and railing installation continue.

In Blocks 30 and 31, aerated concrete walls, plasterboard walls, gypsum plastering, floor heating installations, window framing and installation, mechanical facade anchoring, wet area and flooring marble marble works in wet areas, tile installation on the terrace, and mechanical and electrical works are complete. Facade sealing is at 98% completion. Construction of the swimming pool and manufactures of railings and flooring continue. 

In blocks 27, 28 and 29, aerated concrete walls, gypsum plastering, plasterboard wall and floor heating installation, window framing and installation, and marble installation inside the units and ceramic productions complete. Mechanical facade anchoring and stone facade sealing are at 95% completion, whereas railing installation and pool construction are underway.  

Basic construction and aerated concrete walls for Block 26 is complete. 
Plasterboard wall manufacturing, Mechanical-Electrical works continue.

In Blocks 25, 24, 23 and 22, aerated concrete walls, plasterboard wall, suspended ceiling, marble works for the floors, window framing, mechanical facade works, and mechanical and electrical works are complete. Façade anchoring, window installation, pool construction , ceramic works and railing installation are at 94% completion. 

Aerated concrete wall construction and blind casing installation are finalized for Block 21. Mechanical facade anchoring is 80% complete. Mechanical and electrical works continue.  

Blocks 19 and 20 serve as our model villas. In Block 19 and 20, customer revisions have begun. 

In Blocks 17 and 18, aerated concrete walls, window framing, floor heating installation and plasterboard walls are complete. Reinforced concrete terraces are at 97% completion. Suspended ceilings, electrical and mechanical works, mechanical facade anchoring, railing installation, and swimming pool construction are underway.

In Blocks 15 and 16, aerated concrete walls and floor heating installation are complete. Mechanical facade anchoring is at 90%. Construction of plasterboard walls and suspended ceilings, pool construction and railing installation, electrical and mechanical works, and window framing are underway. 

In Blocks 13 and 14, aerated concrete walls, plasterboard walls, window framing, floor heating installation, and electrical and mechanical works are complete. Mechanical facade anchoring is at 90%. Suspended ceiling and pool construction, and railing installation are underway. 

In Blocks 11 and 12, aerated concrete walls, window framing, floor heating installation, and electrical and mechanical works are complete. Plasterboard wall installation, gypsum plastering, mechanical facade anchoring, pool construction, and railing installation continue.

In Block 10, aerated concrete walls, floor heating installation, terrace insulation and window framing are complete. Installation of plasterboard walls, gypsum plastering, mechanical facade anchoring, construction of the pool, installation of railings and windows, and mechanical and electrical works are underway.

In Block 9, aerated concrete walls, plasterboard walls, mechanical and electrical works, suspended ceilings, gypsum plastering, floor heating installation, terrace insulation, mechanical facade anchoring and window framing are complete. Pool construction, and window and railing installations continue. 


In Block 8, aerated concrete walls, gypsum plastering, plasterboard walls, mechanical and electrical works, terrace insulation, floor heating installation, window framing and suspended ceiling works  are complete. Mechanical facade anchoring, suspended ceilings, pool construction, and window installations continue. 


In Block 7, aerated concrete walls, mechanical and electrical works, floor heating installation, terrace insulation, gypsum plaster works plasterboard wall works and window framing are complete. Mechanical facade cladding works, railing works and pool works are in progress.

In Block 6, aerated concrete walls and plasterboard wall works, underfloor heating works, terrace insulation completed are complete. Construction of plasterboard walls, mechanical facade anchoring, electrical and mechanical works, railing anchoring, pool construction and joinery assembly continue. 

Basic construction, plasterboard wall manufactures, underfloor heating manufacture and aerated concrete walls are finalized in Block 5. Mechanical-Electrical works and gypsum plaster works continue.

In Blocks 3 and 4, aerated concrete walls, plasterboard walls, gypsum plastering, and window framing are complete. Mechanical facade anchoring, installation of railings and windows, mechanical and electrical works, and suspended ceilings are underway. 

In Block 2, aerated concrete walls are complete. Plasterboard wall construction, blind casing installation, and electrical and mechanical works continue. 

In Block 1, aerated concrete walls, electrical and mechanical works, floor heating installation, plasterboard closure works, suspended ceiling manufacture, gypsum plaster works  and window framing are complete. Mechanical facade manufacturing, railing manufacturing, pool manufacturing continues.

Stay tuned for more updates.